Project Details
Owner: Ministry of Forests
Date: October, 2012
Material Supply: Owner
Location: Vavenby Area
Works:
- Replaced existing 15.20m bridge with a 24.38m L x 4.88m W steel girder timber deck bridge on steel pipe risers & precast footings