Project Details

Owner: Ministry of Forests

Date: October, 2013

Material Supply: Owner

Location: Princeton Area

Works:

  • Temporarily installed 9.2m L x 4.27m W bridge;
  • Removed 8.00m L x 1200mm OD Corrugated Steel Pipe (CSP)
  • Installed 11.00m L x 8.46m W skewed concrete slab bridge on lock blocks, concrete no-post barriers & placed rip rap