Naver-Ahbau FSR Bridge Replacement


Warning: Use of undefined constant ids - assumed 'ids' (this will throw an Error in a future version of PHP) in /home/plati018/public_html/wp-content/themes/Platinum/single-projects.php on line 18
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background

Project Details

Owner: Ministry of Forests

Date: August, 2014

Material Supply: Superstructure: Owner Substructure: Platinum Stone Contracting

Location: Hixon Area

Works:

Installed 36.8m L x 4.9m W steel girder bridge with concrete decking on piling; removed existing glulam girder bridge on timber piling; drove 26 steel piles approx. 18m deep; installed piling tie-back system; restored site vegetation

RETURN TO PROJECT GALLERY