Finlay FSR Bridge Designs & Replacements


Warning: Use of undefined constant ids - assumed 'ids' (this will throw an Error in a future version of PHP) in /home/plati018/public_html/wp-content/themes/Platinum/single-projects.php on line 18
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background
Slide background

Project Details

Owner: Ministry of Forests

Date: July, 2013

Material Supply: Platinum Stone Contracting

Location: Mackenzie Area

Works:

  • Designed, supplied & installed 3 double lane and 2 single lane concrete slab bridges, concrete no-post barriers & placed rip rap;
  • 87.2k site: 12.0m L x 9.75m W bridge
  • 96.9k site: 12.0m L x 9.75m W bridge
  • 129.5k site: 12.0m L x 9.75m W bridge
  • 133.5k site: 12.0m L x 4.88m W bridge
  • 135.5k site: 12.0m L x 4.88m W bridge
  • Created temporary road access, including temporary bridge structure, for each site