Project Details

Owner: Ministry of Forests

Date: September, 2014

Material Supply: Platinum Stone Contracting

Location: Prince George Area

Works:

Installed 11.5m L x 4.3m W concrete slab bridge on precast footings; removed existing culvert; hauled & placed rip rap and gravel; completed approach works; restored site vegetation